
The Deadly Psychology of Schedules and
Deadlines
By Barry Blesser
Everyone has experience with projects
that are late, and we have all heard the excuses and explanations — mostly
true — from carpenters, architects, technicians, programmers,
and engineers. In fact, missed project deadlines occurs so frequently
that it is rarely a surprise. If we understood the psychology of
scheduling, planning, and managing, would projects be completed
on time?
The answer is definitely yes, but only if we consider
three fundamental properties of human psychology: our unwillingness
to contemplate the unknown, our inability to envision thousands
of details, and our improved efficiency when deadlines are imminent.
Project leaders study the technical details in schedules, but
they seldom study the psychology of project schedules.
Consider a hypothetical project
of some complexity. Its duration is proportional to the sum of
the time required for completing each of hundreds, if not thousands,
of individual tasks.
What does it mean to estimate the duration
of every task? For tasks that are repeated frequently, we already
have an appreciation for those factors that produce variations
in completion time.
Consider just one task in a
large project: splicing a cable. Some splices take 200 seconds
to complete; some take 180, and some 320. Using the data from
hundreds of splices, we can construct a data table showing how
frequently a splice is completed in a given amount of time. The
extremes might range between 100 and 400 seconds, and the average
time might be 284 seconds. The probability of a splice taking
between 150 and 250 seconds might be 95%. These are the statistical
parameters for the task of one cable splice.
There is no single number for
the time to splice a cable because there are always surprises
and unknowns. Variations in time might arise from an unplanned
interruption by a colleague, a defect in the center conductor,
or a headache after a big lunch. As an exercise, try listing
all those surprises that could influence the time for completing
a familiar task, even the trivial task of brushing your teeth.
Without surprises, the time to splice a cable or to brush your
teeth would be constant and predictable.
For a large project like building
a new studio, which is the composite of many individual tasks,
the total completion time has dramatically larger variation.
By assuming that all tasks have worst-case durations, a project
might take as much as 24 months, and by assuming best-case durations,
a project might take as little as 6 months.
During my 40-year
career, I have never met a leader who overestimated surprises.
Although surprises are an everyday occurrence, they are rarely
analyzed. Yet, the implications of surprises are unacceptable in
projects where there are painful consequences for missing deadlines.
Something has to give.
The easiest solution is to separate
deadlines from the intrinsic variability in a project’s duration.
For example, a leader could select the project’s goals such
that the most likely duration was 30 months, while the actual deadline
was 40 months. The extra 10 months becomes the padding margin for
surprises.
Using statistics, the leader might then compute that
there is a 90% chance of meeting this deadline. But with a deadline
of 30 months, there is only a 50% chance, and with a deadline of
20 months, there is only a 10% chance.
Expectations determine lateness.
With financial budgeting, we never plan to spend the last penny,
and with time budgeting, we should never plan to need the last
hour. If you want to meet a deadline reliably, add margin to the
schedule—the
project will always complete early.
This simple approach fails because
it works against the natural psychology of fear as a source of
motivation. Publish a schedule with 10 months of margin, and
the staff is likely to take long lunch breaks, to arrive late
after a relaxed breakfast, and to socialize when they should
be working. Conversely, if the schedule shows that the project
is modestly late before it begins, the staff is motivated by
a sense of urgency to work diligently. Because efficiency improves
with an immediate deadline, being late becomes a virtue, not
an indication of failure. But if the project is hopelessly late,
the staff gives up because there is no possibility of meeting
the deadline.
Some enlightened leaders use a hybrid approach:
a public schedule without padding (to manage psychology), and
a private schedule with padding (to manage reality).
There are other ways to compensate for
surprises. Separate a project’s requirements into an ordered
list of priorities.
In the example of the studio project, sort tasks
into Phase 1, containing only the minimal requirements to go
on air, and Phase 2, containing those extra requirements that make
the studio cosmetically complete. A studio is still functional
without permanent lighting and dressed cables. Depending on when
Phase 1 actually completes, some, all, or none of the requirements
in Phase 2 can be completed before the deadline. The project
may still be late, but the painful consequences of missing the
deadline have been avoided. Using this approach, a leader compensates
for surprises by dynamically adjusting how many low priority tasks
will be completed.
One reaction to surprises, called thrashing,
guarantees that a project will be very late. Thrashing occurs when
the staff works hard and appears to be making progress, but the
task is never actually completed. This occurs if the requirements
contain hidden contradictions—there
is no possible solution—or if quality expectations are unrealistically
high—perfection is the enemy of good enough.
A thrash-detector
should sound an alarm when a task is not approaching closure at
a rate consistent with the effort being expended.
As an illustration of thrashing, consider
the task of installing a cable between two studios. After installation,
engineers discover that it passes through a region with inordinately
high power-line fields. The hum is an unacceptable –80 dB
while the specification calls for –100 dB. The cable is
then re-installed along a 2nd path, but excessive RF coupling produces
other problems. Again, the cable is again re-installed, but the
3rd path is obstructed by an impenetrable wall. Finally, a specialty
cable is ordered, but it has an unknown delivery time.
Repeated
attempts to find the perfect cable installation, which did not
exist, produced thrashing: doing the same task multiple times.
There
are also examples of contradictory requirements, such as searching
for a full-featured processor that is also small, simple, reliable,
and inexpensive. One could look forever. Sometimes the remedy
for thrashing involves making the task disappear, either because
it is not really needed, or because there is a simple work-around.
Projects will be completed on time
if the leader has an appreciation for surprises. While the specifics
of surprises can never be known beforehand, else they would not
be surprises, an experienced leader anticipates their existence.
He also recognizes the psychology of deadlines, pads the schedule
with margins, sorts task priorities before beginning, and intervenes
when tasks are thrashing. Together, these simple approaches work
like magic for managing a schedule to meet a deadline.
This article was originally published on February
23, 2005 in the Radio World
Engineering Extra column "The Last Word." It is
reproduced here with the author's permission.
Copyright ©2005 by Barry Blesser.
|